Modification of payment period in public procurement
Category: Regulatory
As from January 1st, 2025 a new payment period will apply in public procurement. The separate term for verification and payment of each 30 days and thus 60 days in total, will be replaced by one common “processing period” of maximum 30 days.
The general rule: a processing period
(in Dutch: “behandelingstermijn” and in French: “délai de traitement”)
The rules regarding the payment periods in public procurement result from the Directive 2011/7/EU on combating late payment in commercial transactions, which was transposed to national legislation by the Royal Decree of 14 January 2013.
In a judgment of 20 October 2022 (no C-585/20), the Court of Justice ruled that the aforementioned Directive opposes a national system which provides, in a general manner, for a maximum payment period of 60 calendar days for all commercial transactions between companies and public authorities. The same applies where that period consists of a prior verification period of 30 days followed by an additional period of 30 days for payment.
Since the Royal Decree of 14 January 2013, transposing the Directive, stipulates just such a system, an amendment to that royal decree imposes itself.
Consequently, a single 30-day common “processing period” will apply to new public procurements from 1 January 2025.
Two exceptions on the general rule:
Contracting authorities that provide healthcare services and are specifically authorised for that purpose can apply a processing period of up to 90 days, if the following four cumulative conditions are met:
the contract documents state that a derogation from the general 30-day processing period is being applied (information requirement) and provide for a procedure for acceptance or verification;
the total processing period is no longer than 90 days (maximum 30 days for verification and maximum 60 days for payment);
contracting authorities shall mention the chosen verification period in the contract documents; and
this exception is not used merely to obtain a longer payment period.
In addition, all other contracting authorities (regardless of sector) can apply a processing period of up to 60 days, if the following four cumulative conditions are met:
the contract documents mention the longer processing period (information requirement);
the derogation is objectively justified by the special nature or characteristics of the contract, which does not require that this justification is included in the contract documents;
the processing period may not exceed 60 days; and
an extension of the processing period may not result in manifest unfairness to the contractor.
Some points of attention
The starting point for the processing period depends on the type of contract:
a public works contracts: from receipt of the claim (and any additional documents) and the detailed state of the works by the contracting authority;
a public supply contract: from the supply;
a public service contract: from the establishment of the complete or partial termination of the services, which has been established in writing.
Public service and supply contracts also require a duly issued invoice before the processing period will start.
Finally, the contracting authority will have to complete an electronic form prepared by the FPS Policy and Support. Through this form, data will be obtained for monitoring the processing period.
Key takeaway:As from January 1st, 2025, a new “processing period” (verification and payment) of maximum 30 days (instead of 60 days) will apply in public procurement.
Point of attention: the starting point for the processing period depends on the type of contract. |
Want to know more about payment rules in public procurement? Do not hesitate to contact our Regulatory team.