Liedekerke advises CrossBoundary Energy on the landmark Kamoa-Kakula Solar/BESS Baseload Project in the DRC
Category: Deal Announcement
Liedekerke is proud to have played a key role in bringing the Kamoa-Kakula Solar/BESS Baseload Project into commercial operation near Kolwezi in the Democratic Republic of the Congo by advising CrossBoundary Energy throughout the project.
The project now supplies Kamoa Copper with 30 MW of firm, round-the-clock renewable power. It combines a 233 MWp solar photovoltaic array with a 123 MVA/526 MWh battery energy storage system, demonstrating that renewable energy can be delivered at scale and with the reliability required for major industrial operations.
The project progressed from the signing of the power purchase agreement to commercial operation in just 16 months. Meeting this exceptionally ambitious development and construction timeline required several stages of engineering, procurement, manufacturing, and construction to advance in parallel.
As legal counsel to CrossBoundary Energy, our multidisciplinary team provided advice to CrossBoundary Energy on corporate, regulatory, and compliance matters throughout the development of this flagship project. We supported CrossBoundary Energy's efforts to address every challenge as it came, and played a role in delivering on an exceptionally ambitious development and construction timeline, which is a first for the DRC, and for Africa.
Liedekerke is particularly proud of the trust placed in the firm and of the close and efficient collaboration with the entire CrossBoundary Energy team.
The successful launch of the Kamoa-Kakula Solar/BESS Baseload Project marks an important milestone for the deployment of firm renewable power in the DRC, and demonstrates its potential to support the sustainable development of energy-intensive industrial activities.